Upper Ankhu Khola Hydropower Project

A 44 MW run-of-river hydropower scheme on the Ankhu Khola in Dhading district, Nepal.

Installed Capacity

44 MW

Project Type

Run-of-river (cascade scheme)

Annual Energy

259.44 GWh

River

Ankhu Khola

District

Dhading, Bagmati Province

Status

Under Construction

Overview

Project Description

The Upper Ankhu Khola Hydropower Project is a run-of-river scheme on the Ankhu Khola, a perennial tributary of the Budhi Gandaki River in Dhading district. It is now designed as a cascade scheme, using the regulated tailrace discharge of the upstream Super Ankhu Khola Hydropower Project together with additional flow from the Lapa Khola to generate 44 MW.

Water is diverted at a headpond near Borang village and conveyed through an inverted-U headrace tunnel to an underground powerhouse near Jharlang, driving two vertical-shaft Francis turbines across a gross head of 281.7 m (net head 272.87 m). Because the scheme relies on flow rather than a large storage reservoir, its environmental footprint remains limited while it delivers a steady supply of renewable energy.

Generated electricity is evacuated to the national grid via a 6 km, 132 kV single-circuit transmission line to Borang Substation and sold to Nepal Electricity Authority (NEA) under a power purchase agreement — contributing to Nepal's domestic supply and reducing reliance on dry-season electricity imports.

Technical Details

Key Parameters

River
Ankhu Khola (tributary of Budhi Gandaki)
District / Province
Dhading, Bagmati Province
Rural Municipalities
Rubi Valley RM (headworks) · Khaniyabas RM (powerhouse)
Project Type
Run-of-river cascade scheme
Installed Capacity
44 MW
Annual Energy (Design)
259.44 GWh (dry 78.37 / wet 181.06 GWh)
Gross Head
281.7 m
Net Head
272.87 m
Rated / Design Discharge
18.43 m³/s (2 × 9.215 m³/s per unit)
Catchment Area at Intake
360.79 km² (397.25 km² at powerhouse)
Annual Mean Flow
31.10 m³/s
Headrace Tunnel
Inverted-U tunnel, ~6.85 km total, shotcrete & concrete lining
Powerhouse
Underground — 40.75 m × 20 m × 32 m
Turbines
2 × vertical-shaft Francis, 22.68 MW each
Generators
2 × synchronous salient-pole, 25.88 MVA, 11 kV
Transmission Line
132 kV single circuit, 6 km to Borang Substation
Power Off-taker
Nepal Electricity Authority (NEA)
Construction Period
Approximately 3 years
EPC Contractor
To be confirmed / awarded
Target Commissioning
To be confirmed (per implementation schedule)
Current Status
Under Construction

Progress

Current Status

The project is currently Under Construction. Civil works at the headworks have advanced to the next construction phase (see News, 15 June 2026), and procurement of electromechanical equipment is underway (Invitation for Bids issued 2 May 2026). Detailed milestone tracking and the anticipated commissioning timeline will be published here as construction progresses.